Its common to have understaffed
projects. People get recruited just when the team starts to get behind, but not
before in an attempt from administrative staff to save some money. If team
members can barely finish their jobs on time, they are not very interested in
making advance reports or help you define how much time it will require the
next task. They are tired, and they don’t see the point, since their perception
is that the job gets done just because they don’t get to see their families. In
this scenario is quite difficult to gather information for planning and
control.
Still, if you are at the PMO, you are
aware that knowing the status of the project is as important as doing the job. That
is why it is your job.
How to do it? I found that adapting to
the team worked properly, and try to find information in the format that is
more natural to the person doing the job. Some people have organized tables
where they keep track of everything, some just keep the record in a board with
post-its. I just took their particular methodology, analyze it and talk them
into including additional information I needed. For example, making the reports
with the same periodicity or adding one more field that will allow me to have
the statistics I needed for the reports.
I was able to get normalized data from
all fronts of the project without having every team member filling specific
formats. It just worked for me, and I guess for them, since they never felt my
reports to be a burden.
Just a new remainder that projects are
made by people, and that your need to normalize PM data should never imply you
have to normalize the people you work with.
Managing teams and groups is little trickier and require special skills however sometimes the more normalization bring more complexities.